A two-station inert glovebox workstation under ¥300,000 is achievable if you treat it as a gas-tight system, not just a stainless steel box. The budget must cover the enclosure, antechambers, a regenerative purifier, O2 and H2O analyzers, vacuum, and controls. If you protect leak integrity and purification capacity, the system can hold <1 ppm O2 and H2O for routine air-sensitive work.

Start with the process, not the catalog. Define sample size, solvent exposure, temperature, and daily throughput before you request quotes. A two-operator station usually needs an internal width of 1,200 to 1,500 mm and two glove port pairs, while the antechamber must pass tools and small fixtures without forcing glove changes.

Define the two-station inert glovebox workstation before quoting

For this two-station inert glovebox workstation, specify a 304 stainless steel chamber with continuous welds and a leak rate below 0.05 vol% per hour. The front window should be laminated safety glass or polycarbonate with a scratch-resistant coating. Gloves should be butyl for moisture and solvent resistance, or neoprene if you need better mechanical durability.

Choose one large antechamber and one small quick-transfer chamber if the budget allows. The large chamber should be at least 360 mm diameter or a rectangular 400 x 400 x 400 mm, with a vacuum pump rated for repeated cycling. A small chamber saves purge gas and time for frequent sample entry, but it should not replace the large chamber.

The purifier is the heart of the system. A dual-column design with copper catalyst for O2 removal and molecular sieve for H2O removal is standard. Automatic regeneration, pressure swing logic, and separate O2 and H2O analyzers with <1 ppm resolution are worth more than cosmetic upgrades. Manual regeneration can work, but it adds operator error and downtime.

Budget allocation: where ¥300K should go

In a 300,000 RMB cap, allocate roughly 50,000 to 80,000 RMB for the enclosure, window, gloves, and ports. The purifier and analyzers should take 100,000 to 140,000 RMB. Vacuum, antechambers, valves, and pressure control usually run 30,000 to 50,000 RMB. Controls, PLC, sensors, wiring, installation, gas lines, leak testing, and commissioning add 50,000 to 80,000 RMB.

My recommendation is to buy a domestic purifier with proven regeneration logic and spend the savings on helium leak testing and spare molecular sieve. Imported entry-level gloveboxes often consume the whole budget before analyzers and commissioning. If a quote exceeds 300,000 RMB, cut the automatic antechamber or cosmetic finish, not the purifier or leak test.

Use a rotary vane vacuum pump with an oil mist filter for the antechamber unless your process is extremely clean. A dry scroll pump is better for oil-free operation, but it can add 20,000 to 40,000 RMB; under this budget, a quality rotary vane pump with regular oil changes is the practical choice. Add a pressure relief bubbler and a foot pedal for each operator station.

Commission the two-station inert glovebox workstation step by step

Layout matters as much as components. Place the purifier, vacuum pump, and gas cylinders outside the clean zone with service access. Keep the exhaust and pressure relief line away from operator breathing zones. Two operators need clear floor space, so leave at least 900 mm in front of the gloves and route cables and tubing to avoid tripping.

Commissioning should follow a written sequence: helium leak test, purge with dry nitrogen or argon, purifier regeneration, analyzer calibration, glove leak test, and a 24-hour stability check. Record baseline O2 and H2O levels at idle and during antechamber cycling. A system that reaches <1 ppm in a clean empty state may still rise above 10 ppm when loaded with wet samples, so test with real process materials.

Maintenance planning keeps the workstation inside budget. Replace gloves when they show cracks or discoloration, change vacuum pump oil every 500 to 1,000 hours, and regenerate the purifier when H2O or O2 recovery slows. Keep spare molecular sieve and copper catalyst on site. Label gas lines and post the regeneration procedure near the control panel.

For a practical build under ¥300,000, choose a domestic two-station inert glovebox workstation with a dual-column purifier, one large antechamber, manual gloves, and a rotary vane pump. Put the remaining money into leak testing, analyzers, and commissioning, then validate it with your own samples before final acceptance.

Leave a Reply

Your email address will not be published. Required fields are marked *

Project Delivery
Delivery scope and schedule are defined in the project quotation.
Shipping
Shipping method and terms are defined for each destination.
Installation Planning
Installation and commissioning scope is confirmed per project.
Support Scope
Warranty and service terms are defined in the contract and quotation.